November Phase 3 Update: Approvals Complete

At the November 3 Special Board Meeting, the Board approved the Phase 3 construction task order with Reconstruction Experts (RE) for $1,581,133.24, CTETS supplemental construction-administration services for $40,500, and a $1,890,000 special assessment ($30,000 per unit). The contracts have now been executed.

Phase 3 is moving into preconstruction as the community prepares for January mobilization. RE will begin meeting with owners in Buildings A and B (units 1–7 and 8–15) to inspect the roofs and determine which owner-added items need to be removed before work begins.

Watch the November 3 Special Board Meeting recording  |  View the Phase 3 project details and preparation updates

2027 Budget & Assessment Adoption

Following the Annual Meeting on September 21, 2026, the Board of Directors held a Special Board Meeting and officially adopted the 2027 Budget. The new monthly assessment is established at $595 per unit, effective January 1, 2027. The budget development was driven by the following objective goals:

  • Minimize Increases: The 3.5% (+$20/month) adjustment represents the lowest rate increase in 7 years, achieved through rigorous cost validation and vendor negotiations.
  • Fund Reserves: Fully funds $104,000 in reserve transfers (a $54,000 scheduled contribution plus a $50,000 repayment) to protect lending eligibility and align with the Reserve Study.
  • Correct Maintenance Deficits: Reallocates insurance premium savings directly into Repairs & Maintenance to care for our aging property without relying on special assessments.
  • Plan for Cost Increases: Proactively absorbs projected 5% utility and service inflation, accommodates trash collection hikes, and applies a 10% buffer for insurance rate fluctuations.

View detailed breakdowns and budget comparisons on the Financial Transparency page.

Phase 3 Project Roadmap

The Association is committed to ensuring the long-term structural integrity of our community. Below is an overview of completed repair phases and the current status of Phase 3. View the latest Phase 3 Project updates.

2019 - 2020

Lawsuit & Settlement

The initial construction defect lawsuit was filed in 2019. In April 2020, the Association successfully reached a $1 million settlement agreement. After litigation and engineering costs, approximately $508,430 was secured as a net recovery to assist in funding necessary community repairs.

Completed: 2021

Phase 1: Structural Repairs

Addressed prioritized structural issues, including garage headers and lintels. Work involved flashing, mortar net, and lintel replacements in 30 units, with structural reinforcements in 8 others.

Completed: 2024

Phase 2: Window & Balcony Repairs

Repaired high-priority windows and fully replaced all 63 Juliet balcony doors to address water intrusion pathways.

May 2025 - March 2026

Phase 3A: Investigation & Intrusive Testing

The Association undertook a comprehensive, multi-step investigation to definitively locate the sources of water intrusion. This exhaustive process included Visual Inspections, Aerial IR Drone Surveys, and Targeted Intrusive Testing oversighted by our forensic engineer.

Completed: June 2026

Phase 3B: Engineering Design & Planning

With the physical investigation complete, our forensic engineer CTETS finalized the construction documents to mitigate water intrusion bypassing roof defenses. Temporary parapet waterproofing was installed for priority units during this design phase.

Completed: 2026

Phase 3C: Feedback Integration, Cost Validation & Approvals

Following owner feedback and independent cost validation, the Board approved the Phase 3 construction task order, CTETS supplemental services, and special assessment at the November 3 Special Board Meeting.

Contracts Executed

Phase 3D: Contract Execution

The Association has executed the approved construction and supplemental engineering-services contracts, clearing the way for preconstruction planning ahead of January mobilization.

Current Phase

Phase 3E: Preconstruction & Owner Roof Inspections

RE will begin meeting with owners in Buildings A and B (units 1–7 and 8–15) to inspect the roofs and determine which owner-added items need to be removed in preparation for January mobilization. Please submit questions to the Board.

See Phase 3 Details Here